Airport Meeting RE: Taxiway Closure

PostPosted: Mon May 01, 2017 7:44 pm
by hkraemer
Meeting May 1 2017

Presentation by Delta airport consultants

32 New PAPI

14 taxiway will go to beginning of runway. Dual entries to 14.

Phase 1 is for 60 days

Phase 2 will close entire taxiway for 15 days

Phase 3 will close runway for 10 nights

Night closures will be by notam at least 48 hours in advance

New hold short lines

Pattern work is ok. No touch and goes.

Year 2018


Bravo taxiway is removed.


Dual entries to 32

Here is a PowerPoint presentation by Delta Airport Consultants
http://flymall.org/docs/GAItaxiway2017/ ... y2017.pptx