Meeting May 1 2017
Presentation by Delta airport consultants
32 New PAPI
14 taxiway will go to beginning of runway. Dual entries to 14.
Phase 1 is for 60 days
Phase 2 will close entire taxiway for 15 days
Phase 3 will close runway for 10 nights
Night closures will be by notam at least 48 hours in advance
New hold short lines
Pattern work is ok. No touch and goes.
Year 2018
Bravo taxiway is removed.
Dual entries to 32
Here is a PowerPoint presentation by Delta Airport Consultants
http://flymall.org/docs/GAItaxiway2017/ ... y2017.pptx